Steven Rostedt authored
The current method for pushing RT tasks after scheduling only happens after a context switch. But we found cases where a task is set up on a run queue to be pushed but the push never happens because the schedule chooses the same task. This bug was found with the help of Gregory Haskins and the use of ftrace (trace_printk). It tooks several days for both of us analyzing the code and the trace output to find this. Signed-off-by: Steven Rostedt <srostedt@redhat.com> Signed-off-by: Peter Zijlstra <a.p.zijlstra@chello.nl> LKML-Reference: <20090729042526.205923666@goodmis.org> Signed-off-by: Ingo Molnar <mingo@elte.hu>
da19ab51